East Middleton Force Main Work and CP-2 Blasting
March 9, 2026
The 3:00 PM blasting session was postponed, with no blasting scheduled to follow- at this time.
Crews will continue pump station and pipeline work in the East Middleton area while sewer main installation and site restoration continue in CP-2. Controlled blasting is also scheduled in CP-2 at 11:00 a.m. and 3:00 p.m.
CP-1 Updates
Lewis Electric is on site at the East Middleton Pump Station and will be installing conduit. Park Construction also plans to perform silt fence maintenance to support erosion control in the work area.
Haren crews are continuing piping work within the lift station structure and will also continue installing force main pipe from the pump station area. Additional force main installation will continue between Stardust Lane and West Middleton Drive.
JF Wilkerson crews will continue installing 16-inch force main pipe at the end of East Middleton Drive near the cul-de-sac.
CP-2 Updates
Park Construction crews will continue installing new sewer main pipe and backfilling areas disturbed by construction activity.
Carolina Drilling is scheduled to perform controlled blasting at 11:00 am and 3:00 pm.