Construction Package 1 and 2 Work Continues with Ongoing Will Suitt Road Activity
April 30, 2026
CP1 Updates
Haren Construction crews will continue pipe installation at the Joe Peed site. JFW crews will resume gravity sewer line work at the East Middleton Lift Station and continue landscaping activities along East Middleton Drive. Autry crews will continue force main work on West Middleton Drive.
CP2 Updates
Park Construction crews will continue laying 36-inch fiberglass reinforced polymer pipe along Will Suitt Road en route to Sanitary Manhole 3058. Carolina Drilling crews are scheduled to conduct one controlled blast today at the Interstate 85 bore pit at 2:00 pm.
Traffic Impacts
The closure of Will Suitt Road will remain in effect through Friday.