Joe Peed, Middleton Drive, and Will Suitt Road Work Continues as Road Reopening Approaches
May 1, 2026
CP1 Updates
Haren Construction crews will continue pipe installation at the Joe Peed site. JFW crews will resume gravity sewer line work at the East Middleton Lift Station and continue landscaping activities along East Middleton Drive. Autry crews will continue force main work on West Middleton Drive.
CP2 Updates
Park Construction crews will begin dressing up the work area along Will Suitt Road. Crews will also begin moving equipment and materials to the launch pit access road. Carolina Drilling crews are scheduled to conduct one controlled blast today at the I-85 bore pit at 11:00 am.
Traffic Impacts
Will Suitt Road is expected to reopen today at the close of business.
Traffic Update: Will Suitt Road is now open to traffic following utility construction, roadway crossing work, and restoration activities associated with the I-85 Sanitary Sewer System Improvement Project.
Thank you for your patience during this process.