Joe Peed Road Pipe Installation and Railroad Avenue Blasting Activity

June 2, 2026

CP-1 Updates
Haren staff will continue pipe installation activities at the Joe Peed site. JF Wilkerson crews will continue laying gravity sewer main along Joe Peed Road. Autry crews will continue force main work on West Middleton Drive.

CP-2 Updates
Park Construction staff will continue installing the 36-inch fiberglass reinforced pipe at the launch pit. Carolina Drilling staff is scheduled to conduct one blast today at 2:00 PM on Railroad Avenue.

Update 7:00 PM: The I-85 SSI Project Pipeline work has progressed to East Lyon Station Road, with the construction contractor planning to cross East Lyon Station Road from West Middleton Drive. This work will require a temporary one-lane closure, beginning June 3rd, while crews complete the crossing.