Middleton Drive Force Main and Receiving Pit Pipe Installation

April 15, 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews will continue 16-inch force main installation along Middleton Drive. JFW restoration crews are stripping driveway forms and dressing disturbed areas. JFW crews also used the hydraulic broom to sweep East Middleton Road.

CP-2
Park crews will begin laying 36-inch fiberglass reinforced polymer pipe from the receiving pit out toward Will Suitt Road. Carolina Drilling crews are scheduled to conduct one blast at the Interstate 85 bore pit at 2:00 pm.