Middleton Drive Force Main and Receiving Pit Pipe Installation

April 14, 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews will continue 16-inch force main installation along Middleton Drive. JFW restoration crews are also working to replace concrete driveways.

CP-2
Park crews will begin laying 36-inch fiberglass reinforced polymer pipe from the receiving pit out toward Will Suitt Road. Carolina Drilling crews are scheduled to conduct one blast at the Interstate 85 bore pit at 2:00 pm.