Middleton Drive Force Main and I-85 Bore Pit Blasting
April 8, 2026
CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews will continue 16-inch force main installation along Middleton Drive. Autry crews are installing 24-inch force main along West Middleton Drive.
CP-2
Park crews are continuing to lay fiberglass reinforced polymer pipe along Eighth Street in areas that have already been blasted. Carolina Drilling crews will begin blasting at the Interstate 85 bore pit. Crews are on the Fire Marshal’s schedule to conduct blasting near Interstate 85 South today at 11:00 am and 2:30 pm.