Middleton Drive Force Main and Eighth Street Installation

March 30, 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews have resumed 16-inch force main installation along Middleton Drive.

CP-2
Park crews are continuing 36-inch fiberglass reinforced polymer pipe installation from Manhole 1144 across Eighth Street, with plans to set Manhole 5750 today.

Carolina Drilling crews are scheduled to conduct one blast on West D Street at 8:30 am and one blast at the micro tunnel site at 12:00 pm.