top of page
Joe Peed Road Sewer Installation, West Middleton Force Main Work, and CP-2 Controlled Blasting
May 19, 2026
Construction Package 1 (CP1)
At the Joe Peed Road site, Haren Construction crews will continue pipe installation activities. JF Wilkerson crews are scheduled to resume gravity sewer main installation along Joe Peed Road. Autry crews will continue force main work along West Middleton Drive.
Construction Package 2 (CP2)
Park Construction crews will continue installing the 36-inch fiberglass reinforced pipe at the launch pit.
Carolina Drilling crews are scheduled to conduct two controlled blasts today, with the first planned for approximately 11:00 AM and the second planned for approximately 2:00 PM.

bottom of page












