May 23 - June 6

Construction Sites

Please be advised that noise disruptions may occur during the construction activities. Clearing may begin as early as 7:00 AM.

HCCI noted that the majority of the work has been clearing the sites and preparing for
construction.

o Clearing at Joe Peed is complete, erosion control measures installed, and they are currently working on the blasting.

o Clearing at East Middleton is complete, erosion control measures installed, and they
are prepping for the undercut of the unsuitable soils.

o After blasting at Joe Peed is complete, they plan to switch the crew over to East Middleton to do the same.

o Wilkerson noted that they have completed the clearing along the pipeline alignments as well.