Joe Peed Force Main Installation and 36-Inch FRP Work at the Launch Pit

May 8, 2026

Construction Package 1 crews will continue work in the Joe Peed and West Middleton project areas. Haren Construction crews will continue pipe installation at the Joe Peed site. JF Wilkerson crews have resumed force main installation at the Joe Peed site. Autry crews will continue force main work along West Middleton Drive.

Construction Package 2 crews will continue work at the launch pit and near the Will Suitt Road pipe installation area. Park Construction crews have resumed installation of the 36-inch fiberglass reinforced polymer pipe at the launch pit and will continue loading out soil from the Will Suitt Road pipe installation area.

Carolina Drilling is scheduled to conduct one controlled blast today at 11:00 am.