top of page
Construction Workers Measuring

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

SOCIOS DEL PROYECTO

Consulte la información diaria del plan de trabajo de campo del Proyecto de Mejora del Alcantarillado Sanitario I-85 de SGWASA, recibida de los Representantes Residentes del Proyecto.

Próxima actualización:

19 de agosto de 2026

18 de agosto de 2026

Railroad Avenue Pipe Placement and Microtunnel Operations Move Forward

CP-1 Updates
Haren is advancing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.

CP-2 Updates
Park crews are placing 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue as underground utility installation progresses.

Young Construction is advancing microtunnel operations.

I-85 SSI Project work currently reflects the steady, coordinated progress behind major wastewater infrastructure improvements.

Activity remains focused on the Joe Peed lift station, sewer installation along Joe Peed Road, sewer force main work, 36-inch fiberglass-reinforced pipe placement on Railroad Avenue, and microtunnel operations.

Actualizaciones de construcción:

3/8/26, 8:05 p.m.

This week, crews plan to complete the 8-inch waterline, restore the gravity sewer right-of-way, install the 24-inch valve near Will Suitt Road, and continue restoration along West Middleton Drive. Next week, work will include grading along the gravity sewer alignment on Joe Peed Road and beginning installation of the 20-inch force main from the Joe Peed Pump Station. Flagging will be used as needed along Joe Peed Road, East Lyon Station Road, West Middleton Drive, and East Middleton Drive. A lane closure is planned on Joe Peed Road during force-main installation. No utility service impacts are anticipated.

Park Construction crews will continue pipe installation along Railroad Avenue, while Young Construction begins advancing the microtunnel casing, with progress dependent on rock conditions. Blasting remains on hold. Full road closures are anticipated on Laundry Avenue and Railroad Avenue near active construction areas. No utility service impacts are anticipated.

Site cleanup and maintenance activities are planned for 8th Street, in Butner, NC.

Actualizaciones de noticias

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.
bottom of page