top of page
Construction Workers Measuring

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

SOCIOS DEL PROYECTO

Consulte la información diaria del plan de trabajo de campo del Proyecto de Mejora del Alcantarillado Sanitario I-85 de SGWASA, recibida de los Representantes Residentes del Proyecto.

Próxima actualización:

9 de noviembre de 2026

6 de noviembre de 2026

Rock Removal Supports Railroad Avenue Pipeline Connection Work

CP-1 Updates
Haren maintains construction activity at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is progressing with sewer line installation, while Autry is installing the sewer force main.

CP-2 Updates
Park Construction is working to connect the Norfolk Southern Railroad bore pipe to the previously installed pipeline along Railroad Avenue. Crews are also hammering through rock encountered during this portion of the installation.

No controlled blasting is scheduled today on C Street.


Rock removal remains part of today's I-85 SSI construction activity as Park Construction works to connect the Norfolk Southern Railroad bore pipe to the previously installed pipeline along Railroad Avenue. Crews are continuing to break through rock to accommodate the connection, while CP-1 operations remain active at the Joe Peed lift station and along Joe Peed Road. No blasting is scheduled today on C Street.

Actualizaciones de construcción:

4/11/26, 12:21 p.m.

Construction continues across several I-85 SSI Project work areas. Park Construction plans to complete the railroad and microtunnel tie-ins before returning to 8th Street at C Street to finish remaining sewer installation. Work on 8th Street is nearing completion, with final paving tentatively planned before Thanksgiving.

Blasting continues along C Street, where intermittent gas service impacts remain possible. Final paving is also planned for 8th Street and Railroad Avenue.

Along Joe Peed Road, crews will continue 20-inch force-main installation, with traffic flagging and periodic lane closures used as necessary. Next week, installation is planned to continue between WB Clark Road and East Lyon Station.

Traffic Impacts
- 8th Street: Full Closure
- C Street: Full Closure
- Railroad Avenue: Partial Closure
- Joe Peed Road: Periodic lane closures
Please follow posted traffic controls and use caution around active work zones.

Actualizaciones de noticias

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.
bottom of page