
Proyecto SSI I-85
La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.
Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.
SOCIOS DEL PROYECTO
Consulte la información diaria del plan de trabajo de campo del Proyecto de Mejora del Alcantarillado Sanitario I-85 de SGWASA, recibida de los Representantes Residentes del Proyecto.
Próxima actualización:
19 de octubre de 2026
16 de octubre de 2026
8th Street Pipe Installation Remains the Focus of CP-2 Work
CP-1 Updates
Haren continues work at the Joe Peed lift station.
Along Joe Peed Road, JF Wilkerson continues sewer line installation, while Autry continues sewer force main construction.
CP-2 Updates
Park continues pipe installation on 8th Street.
SGWASA appreciates the community’s continued awareness around active construction areas as crews move work forward.

CP-1 work continues at the Joe Peed lift station and along Joe Peed Road, while Park maintains pipe installation on 8th Street.
Actualizaciones de construcción:
14/10/26, 11:18 a.m.
During the week of OCT 12, 2026, crews will continue the 20-inch force main from Joe Peed, complete the WB Clark Road crossing, begin pipe installation on 8th Street, continue blasting along C Street, and complete final paving on Laundry Avenue and Railroad Avenue. Pipe installation on A Street has been completed, with paving preparation underway.
During the week of OCT 19, force-main installation is planned to continue between WB Clark Road and E. Lyon Station, while work near E. Lyon Station and East Middleton Drive begins.
At the Norfolk Southern Railroad crossing, pipe supports, carrier pipe, and bulkheads are scheduled for installation OCT 19–20, followed by receiving-pit backfill OCT 21–23. Young will also obtain casing spacers and thread the pipe through the completed microtunnel casing.
Closures:
- WB Clark Road: Closed to through traffic OCT 14–16 for the force-main crossing
- 8th Street: Full closure anticipated as pipe installation progresses
- C Street: Full closure anticipated as blasting continues
- A Street: Full closure anticipated as applicable to active construction
Some service impacts are anticipated on 8th Street, with possible intermittent water and/or gas impacts along C Street as blasting continues.

