Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

SOCIOS DEL PROYECTO

Consulte la información diaria del plan de trabajo de campo del Proyecto de Mejora del Alcantarillado Sanitario I-85 de SGWASA, recibida de los Representantes Residentes del Proyecto.

Próxima actualización:

8 de junio de 2026

5 de junio de 2026

FRP Installation continues and Saturday work has been planned

CP-1 Updates
Haren staff continuing pipe installation at Joe Peed site

JFW -Staff continues laying gravity sewer main on Joe Peed Rd.
Autry - FM work on West Middleton

CP-2 Updates-
Park Staff to continue installing the 36" FRP restrained joint pipe installation in the launch pit access road. Staff will also be hauling spoil from Railroad Ave and launch pit access road.
Park staff will continue E&SC repairs along the launch pit access road.
Carolina Drilling staff will conduct blast today, 10:00am on Railroad Ave

**Park staff plans to work on Saturday, they will be hauling spoil from the site.

Actualizaciones de construcción:

3/6/26, 1:58 a.m.

Progress continues on the I-85 Sanitary Sewer Improvement Project, with crews advancing another important section of sewer infrastructure along the project corridor. As part of this progress, residents, commuters, and nearby property owners are encouraged to plan ahead for a temporary travel pattern change scheduled for Wednesday, June 3rd, 2026.

Project activity is scheduled to continue along Joe Peed Road, East Middleton, West Middleton Drive, East Lyon Station Road, A Street, 8th Street, and Central Avenue.

Work will include force main installation, gravity sewer activity, valve and electrical building improvements, odor-control preparation, wet well coating work, electrical ductbank installation, microtunnel-related pipe installation, and controlled blasting on West A Street.

🚧 Important Travel Notice Beginning June 3rd, 2026 🚧

Pipeline work has progressed to East Lyon Station Road, and the contractor is scheduled to cross East Lyon Station Road from West Middleton Drive on Wednesday, June 3rd. This work is a key step in moving the project forward and will require a temporary one-lane closure while crews complete the crossing.

Traffic control will be in place, and drivers should anticipate brief delays, reduced travel speeds, and active construction near East Lyon Station Road and West Middleton Drive. Drivers traveling through this area are encouraged to allow additional travel time and exercise caution.

No planned water or sewer service interruptions are anticipated at this time.