East Middleton Force Main and FRP Sewer Main Work
13 de marzo de 2026
Haren teams are preparing valve vault assemblies and may also pour grout within the vault.
JFW/Autry crews are continuing work on the 16-inch force main along East Middleton Drive and are currently active at West Middleton Drive, where 24-inch force main installation is underway.
CP-2 Updates
Park staff will continue installing FRP sewer mains and backfilling disturbed areas. Crews will also continue grouting pipe inverts inside manholes.
No blasting is scheduled for today.