East Middleton Force Main Work and CP-2 Blasting

9 de marzo de 2026

The 3:00 PM blasting session was postponed, with no blasting scheduled to follow- at this time.

Crews will continue pump station and pipeline work in the East Middleton area while sewer main installation and site restoration continue in CP-2. Controlled blasting is also scheduled in CP-2 at 11:00 a.m. and 3:00 p.m.


CP-1 Updates

Lewis Electric is on site at the East Middleton Pump Station and will be installing conduit. Park Construction also plans to perform silt fence maintenance to support erosion control in the work area.

Haren crews are continuing piping work within the lift station structure and will also continue installing force main pipe from the pump station area. Additional force main installation will continue between Stardust Lane and West Middleton Drive.

JF Wilkerson crews will continue installing 16-inch force main pipe at the end of East Middleton Drive near the cul-de-sac.

CP-2 Updates

Park Construction crews will continue installing new sewer main pipe and backfilling areas disturbed by construction activity.

Carolina Drilling is scheduled to perform controlled blasting at 11:00 am and 3:00 pm.

logotipo de sgwasa

Autoridad de agua y alcantarillado del sur de Granville

415 Avenida Central, Suite B

Butner, Carolina del Norte 27509

​

​

TELÉFONO

(919) 575-3367

​

​

FAX

​

​

(919) 575-4547

Archivo

Financiero

Contacto del personal

nuevos clientes

Clientes existentes

© Derechos de autor
bottom of page