Joe Peed, Middleton Drive, and Will Suitt Road Work Progress

23 de abril de 2026

CP1 Updates
Haren Construction crews will continue pipe installation at the Joe Peed site. JFW crews will continue installation of the 16-inch force main along East Middleton Drive. Autry crews will continue pipe installation on West Middleton Drive.

CP2 Updates
Park Construction crews will continue laying 36-inch fiberglass reinforced polymer pipe from the receiving pit toward Will Suitt Road. Blasting operations are paused for today.

Norfolk Southern is conducting railroad track work near 26th Street and has restricted access in that area for the day. The area is expected to be cleared tomorrow, at which time blasting operations are expected to resume.

Traffic Impacts
Crews remain on schedule for the planned closure of Will Suitt Road beginning Monday, April 27th, at 8:30 am. Any changes to that schedule will be communicated as updates become available.