FRP Installation continues and Saturday work has been planned

5 de junio de 2026

CP-1 Updates
Haren staff continuing pipe installation at Joe Peed site

JFW -Staff continues laying gravity sewer main on Joe Peed Rd.
Autry - FM work on West Middleton

CP-2 Updates-
Park Staff to continue installing the 36" FRP restrained joint pipe installation in the launch pit access road. Staff will also be hauling spoil from Railroad Ave and launch pit access road.
Park staff will continue E&SC repairs along the launch pit access road.
Carolina Drilling staff will conduct blast today, 10:00am on Railroad Ave

**Park staff plans to work on Saturday, they will be hauling spoil from the site.