East Middleton Force Main Work and CP-2 Outfall Blasting

11 de marzo de 2026

CP-1 Updates
Haren staff continues working on backfill and cleanup around PS.
Lewis Electric continuing conduit installation at East Middleton.

JFW - Continue working on 16" FM coming up east middleton dr. Working in between Stardust Lane and West Middleton dr, installing 24" FM.

CP-2 Updates
Park staff to continue installing FRP sewer mains and backfilling disturbed areas.

Carolina Drilling will blast a section of rock in the outfall at 10:00 am and 1:00 pm. This section is not in the roadway so is not under the "stop work" order from Enbridge.