Joe Peed Road Gravity Sewer Work and Railroad Avenue Blasting Activities

3 de junio de 2026

CP-1 Updates
Haren staff are continuing pipe installation activities at the Joe Peed site. JFW staff are also progressing with gravity sewer main installation along Joe Peed Road. Autry crews are performing force main work on West Middleton Drive as part of ongoing utility improvements in the project area.

CP-2 Updates
Park Construction staff will continue installing 36-inch fiber-reinforced polymer pipe at the launch pit. Crews will also begin excavation over the gas transmission main to support installation of the steel casing. Enbridge staff will be on site to monitor conditions while this work is underway.

Park Construction staff will also continue erosion and sediment control repairs along the launch pit access road. Carolina Drilling is scheduled to conduct blasting activities on Railroad Avenue, at approximately 11:00 AM and 2:00 PM today, with an additional blast scheduled for tomorrow at approximately 10:00 AM and 2:00 PM.


bottom of page