Railroad Avenue Pipe Installation Wraps Up as Service Connections Begin on 8th Street
16 de noviembre de 2026
CP-1 Updates
Haren remains engaged in construction at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is carrying out sewer line installation, while Autry is advancing work on the sewer force main.
CP-2 Updates
Park Construction maintains pipe installation activities along 8th Street and C Street. Crews are scheduled to complete its remaining pipe installation on Railroad Avenue before relocating to 8th Street to begin connecting service lines.
Carolina Drilling plans to conduct one controlled blast today at 1:00 PM.
Motorists should remain attentive to posted traffic guidance and use caution when traveling near active construction sites.