Railroad Avenue Work Advances as Pipe Pushing Begins at the NSR Bore
23 de octubre de 2026
CP-1 Updates
Haren remains active at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is moving sewer line installation forward while Autry progresses sewer force main work.
CP-2 Updates
Park Construction will set a sewer manhole on Railroad Avenue before the Norfolk Southern Railroad receiving pit. Crews will also continue cleanup along 8th Street and C Street.
Young Construction will begin pushing pipe through the Norfolk Southern Railroad bore casing, moving this portion of the underground installation into its next stage. Carolina Drilling will not conduct blasting today.
SGWASA appreciates the community’s continued awareness as crews coordinate underground installation and cleanup across the active work areas.