Railroad Avenue Blasting Scheduled as Microtunnel Work Moves Forward

12 de agosto de 2026

CP-1 Updates
Haren is working at the Joe Peed lift station. JF Wilkerson is installing sewer line along Joe Peed Road. Autry is performing sewer force main work along Joe Peed Road.

CP-2 Updates
Park crews are placing 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction is advancing microtunnel operations. Carolina Drilling is scheduled to conduct two controlled blasts today on Railroad Avenue, with one planned for 9:00 AM and another planned for 12:00 PM noon.
________
9:28 AM Update:

12:00 PM Blasting plans have been rescheduled for 2:00 PM.