A Street Pipe Laying Resumes with 8th Street Blasting Scheduled

14 de septiembre de 2026

CP-1 Updates
Haren is working at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.

CP-2 Updates
Park resumes pipe laying activities on A Street; and is also working on air gap and heave removal on 8th Street. Young Construction is advancing I-85 microtunnel boring, a second Young Construction crew is carrying Norfolk Southern Railroad boring activities forward.

Carolina Drilling is scheduled to conduct two controlled blasts today on 8th Street at 11:00 AM and 3:00 PM.