CP-1 Updates
Haren is working at the Joe Peed lift station.
Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.
CP-2 Updates
Park is moving forward with pipe laying activities on A Street, and is also addressing air gap and heave removal on 8th Street. Young Construction is advancing I-85 microtunnel boring.
A second Young Construction crew is performing Norfolk Southern Railroad boring activities. Carolina Drilling is scheduled to conduct two controlled blasts today on 8th Street at 11:00 AM and 3:00 PM.