Railroad Avenue Pipe Installation Advances with Microtunnel Operations
7 de agosto de 2026
CP-1 Updates
Haren is progressing work at the Joe Peed lift station. JF Wilkerson is installing sewer line along Joe Peed Road. Autry is performing force main work near Lyon Station Road.
CP-2 Updates
Park crews are placing 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction is advancing microtunnel operations.
3:00 PM Update:
Crews have encountered high-bottom rock, meaning rock remains above the required excavation depth.
Carolina Drilling has been asked to complete blasting for Park Construction to support continued work at SMH #5778.