Railroad Avenue Work Carries Forward with Underground Progress
21 de agosto de 2026
CP-1 Updates
Haren is moving work forward at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry advances sewer force main work.
CP-2 Updates
Park crews are placing 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction is progressing microtunnel operations.