8th Street Blast Scheduled as A Street Excavation Continues

4 de septiembre de 2026

CP-1 Updates
Haren is advancing work at the Joe Peed lift station.

Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.

CP-2 Updates
Park is continuing excavation on A Street.

Young Construction has a limited crew onsite to service equipment and maintain field readiness.

Carolina Drilling is scheduled to conduct one controlled blast today on 8th Street at 11:00 AM. Park will suspend all site operations at noon today, resuming work on Tuesday.