8th Street Blasting Scheduled as Remediation and Paving Work Advances

9 de septiembre de 2026

CP-1 Updates
Haren is advancing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.

CP-2 Updates
Park crews are addressing failed compaction areas on Laundry Avenue and Railroad Avenue. Crews are also working on air gap and heave removal on 8th Street.

ASD is onsite performing paving operations on Railroad Avenue. Young Construction has a limited crew onsite. Replacement cutting discs are expected this week, with the arrival date to be determined. Boring operations will resume once the discs are installed.

Carolina Drilling is scheduled to conduct two controlled blasts today on 8th Street at 11:00 AM and 3:00 PM.