Northern Interceptor Test Drilling Adds a New Field Activity to Today’s Schedule
6 de octubre de 2026
CP-1 Updates
Haren is advancing work at the Joe Peed lift station.
Along Joe Peed Road, JF Wilkerson continues sewer line installation while Autry progresses sewer force main construction.
CP-2 Updates
Park is continuing pipe installation along A Street.
Young Construction continues dismantling the tunnel boring machine (TBM) as work progresses through this phase of the tunneling operation.
A second Young Construction crew continues Norfolk Southern Railroad bore activities.
Carolina Drilling is scheduled to conduct one controlled blast today at 2:00 PM. Crews will also perform test drilling for the Northern Interceptor.