One Controlled Blast Scheduled on Railroad Avenue Today
17 de agosto de 2026
CP-1 Updates
Haren is advancing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.
CP-2 Updates
Park crews are placing 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue as underground utility installation progresses.
Young Construction is advancing microtunnel operations. Carolina Drilling is scheduled to conduct one controlled blast today on Railroad Avenue at 10:00 AM.