top of page
Central Avenue Crossing Work Continues as Manhole Coating Testing Begins
8 de julio de 2026
CP-1 Updates
Haren crews remain focused on continuing pipe installation at the Joe Peed site. JF Wilkerson crews are continuing sewer line work along Joe Peed Road. Autry crews are continuing force main work crossing East Lyon Station Road.
CP-2 Updates
Park staff are continuing installation of 36-inch fiberglass-reinforced pipe (FRP) on A Street as work advances across Central Avenue. Detour processes remain in place to support traffic movement around the active work area.
TPT Coatings staff are onsite conducting holiday testing on manholes located along the receiving pit access road.