top of page

Joe Peed Road Sewer Installation and A Street Blasting Completion

29 de mayo de 2026

CP-1 Updates
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews continue laying gravity sewer main along Joe Peed Road as part of ongoing sewer infrastructure improvements.

Autry crews are continuing force main work along West Middleton Drive.

CP-2 Updates
Park Construction crews will continue installing the 36-inch fiberglass reinforced pipe at the launch pit. Kelly’s NCEC crews will be on site completing seeding and strawing work at the receiving pit outfall and along the Will Suitt Road shoulder.

Carolina Drilling is scheduled to conduct one controlled blast today at approximately 10:00 AM, which is expected to complete blasting activity along A Street.

Nearby residents, motorists, and property owners may notice temporary noise or vibration associated with this planned construction activity.


bottom of page