top of page

Railroad Avenue Pipe Work Resumes as A Street Restoration Preparation Continues

27 de octubre de 2026

CP-1 Updates
Haren continues work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is progressing sewer line installation while Autry advances sewer force main construction.

CP-2 Updates
Park Construction will begin preparing the remaining portion of A Street for milling and overlay.

Crews will resume pipe installation on Railroad Avenue downstream of the Norfolk Southern Railroad bore receiving pit.

On C Street, Park will excavate a gas line air gap in support of upcoming construction activities.

Carolina Drilling is scheduled to conduct one controlled blast today at 1:00 PM. Young Construction will begin preparations for pushing pipe through the microtunnel casing.


bottom of page