8th Street Pipe Work Continues Alongside Paving and Underground Preparation
13 de octubre de 2026
CP-1 Updates
Haren continues work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson continues sewer line installation, while Autry continues sewer force main construction.
CP-2 Updates
Park is continuing pipe installation on 8th Street. ASD is onsite conducting asphalt overlay work on Laundry Avenue, Railroad Avenue, and 19th Street.
Young Construction is continuing preparation for pipe-pushing activities at the Norfolk Southern Railroad bore and microtunnel sites.
Carolina Drilling is scheduled to conduct one controlled blast on C Street at 1:00 PM.