C Street Preparation Continues as A Street Paving Advances
15 de octubre de 2026
CP-1 Updates
Haren continues work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson continues sewer line installation, while Autry continues sewer force main construction.
CP-2 Updates
Park continues pipe installation on 8th Street. On C Street, Park will excavate air gaps around the gas and water lines in preparation for Carolina Drilling.
ASD will begin placing the asphalt base coat from the National Guard area toward Mt. Hope PS.
No controlled blasting is scheduled for today. Enbridge notified the project team that personnel are not available to conduct the required pre- and post-blast surveys. Carolina Drilling plans to resume drilling Monday.
SGWASA appreciates the community’s continued awareness as crews coordinate pipeline construction, roadway restoration, and preparation for upcoming work.