top of page

A Street Sewer Installation Continues Across Central Avenue

17 de julio de 2026

CP-1 Updates
Haren continues pipe installation at the Joe Peed site. JF Wilkerson continues sewer line installation along Joe Peed Road. Autry continues force main work near East Lyon Station Road.

CP-2 Updates
Park crews continue installation of the 36-inch fiberglass-reinforced pipe (FRP) on A Street as work advances across Central Avenue. Young Construction continues bore pit work off Will Suitt Road.