Middleton Drive Force Main and Receiving Pit Pipe Installation

13 de abril de 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews will continue 16-inch force main installation along Middleton Drive. Autry crews will return the week of April 20 to continue installing 24-inch force main along West Middleton Drive.

CP-2
Park crews will begin laying 36-inch fiberglass reinforced polymer pipe from the receiving pit out toward Will Suitt Road. Carolina Drilling crews are scheduled to conduct one blast at the Interstate 85 bore pit at 2:00 pm.