Middleton Drive Force Main and Eighth Street FRP Installation

6 de abril de 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews will continue 16-inch force main installation along Middleton Drive. Autry crews are installing 24-inch force main along West Middleton Drive.

CP-2
Park crews are continuing to lay fiberglass reinforced polymer pipe along Eighth Street in areas that have already been blasted. Carolina Drilling crews will mobilize equipment upstream of the bore pit and plan to begin drilling and blasting from Interstate 85 to Railroad Avenue.