top of page
Middleton Drive Force Main and I-85 Bore Pit Blasting
9 de abril de 2026
CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews will continue 16-inch force main installation along Middleton Drive. Autry crews are installing 24-inch force main along West Middleton Drive.
CP-2
Park crews are continuing finish grade work on 8th Street. Crews will also begin mobilizing equipment to the microtunnel receiving pit to begin pipe installation in areas that have already been blasted. Seeding and strawing will continue in disturbed areas near the pipe outfall off D Street. Carolina Drilling crews will begin blasting at the Interstate 85 bore pit. Crews are on the Fire Marshal’s schedule to blast near Interstate 85 South today at 11:00 am and 2:30 pm.

bottom of page