Joe Peed Pipe Installation and Eighth Street Progress

27 de marzo de 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews are dressing up the site today, and no pipe installation is scheduled.

CP-2
Park crews are continuing 36-inch fiberglass reinforced polymer pipe installation from Manhole 1144 across Eighth Street. Carolina Drilling crews are scheduled to conduct one blast at the microtunnel site at 11:30 am.