Force Main Work Continues as CP-2 Blasting Proceeds

23 de marzo de 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews are continuing 16-inch force main installation along East Middleton Drive.

CP-2
Park crews are continuing 36-inch FRP pipe installation across D Street. Carolina Drilling crews are scheduled to conduct blasting at the microtunnel site at 10:30 am and 2:30 pm. West D Street blasting is also scheduled for 11:00 am and 3:00 pm.

11:25 AM Update: No blasting will occur on D Street today, as crews require additional time to hammer through rock encountered within the work area.