East Middleton Force Main and CP-2 Blasting Operations

24 de marzo de 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews are continuing 16-inch force main installation along East Middleton Drive.

CP-2
Park crews are continuing 36-inch FRP pipe installation across D Street. Carolina Drilling crews are scheduled to blast at the microtunnel site at 10:30 am and 2:30 pm. West D Street blasting is scheduled for 8:00 am and 1:00 pm.