East Middleton Force Main and Eighth Street Pipe Installation

26 de marzo de 2026

CP-1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews are continuing 16-inch force main installation along East Middleton Drive.

CP-2
Park crews are continuing 36-inch fiberglass reinforced polymer pipe installation from Manhole 1144 across Eighth Street. Carolina Drilling crews are scheduled to blast at the microtunnel site at 10:30 am and 2:30 pm. No blasting is scheduled on West D Street today. ADS Paving is on site to mill the D Street trench area and repave the road cut.