Joe Peed Pipe Installation and D Street Progress
25 de marzo de 2026
CP 1
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews are continuing 16-inch force main installation along East Middleton Drive.
CP 2
Park crews are continuing 36-inch fiberglass reinforced polymer pipe installation across D Street. Carolina Drilling crews are scheduled to conduct blasting at the microtunnel site at 10:30 am and 2:30 pm. No blasting is scheduled on West D Street today.