Joe Peed Site, Middleton Drive, and I-85 Bore Activity
17 de abril de 2026
Contract Package 1 Updates
Haren Construction crews will continue pipe installation at the Joe Peed site. JFW crews will continue installation of the 16-inch force main along East Middleton Drive. Autry crews will resume pipe installation on West Middleton Drive.
Contract Package 2 Updates
Park Construction crews will continue installing 36-inch fiberglass reinforced polymer pipe from the receiving pit toward Will Suitt Road. Carolina Drilling crews are scheduled to conduct one blast at the Interstate 85 bore pit at 1:00 p.m. Kelly’s crews will continue seeding and strawing disturbed areas along 8th Street and D Street.