Joe Peed Pipe Installation, West Middleton Force Main Work, and Launch Pit FRP Activity
13 de mayo de 2026
Construction Package 1 crews will continue work in the Joe Peed and West Middleton project areas. Haren Construction crews will continue pipe installation at the Joe Peed site. JF Wilkerson crews are not scheduled to be onsite today. Autry crews will continue force main work along West Middleton Drive.
Construction Package 2 crews will continue work at the launch pit. Park Construction crews will continue installing the 36-inch fiberglass reinforced polymer pipe at the launch pit.
Carolina Drilling is scheduled to conduct one controlled blast today at 2:00 pm. SGWASA encourages residents and motorists near active work zones to remain alert, follow posted signage, and use caution around crews and equipment.