Joe Peed Road Sewer Installation, West Middleton Force Main Work, and CP-2 Launch Pit Activity

18 de mayo de 2026

Construction Package 1
At the Joe Peed Road site, Haren Construction crews will continue pipe installation activities. JF Wilkerson crews are scheduled to resume gravity sewer main installation along Joe Peed Road. Autry crews will continue force main work along West Middleton Drive.

Construction Package 2
Park Construction crews will continue installing the 36-inch fiberglass reinforced pipe at the launch pit.
Carolina Drilling crews are scheduled to conduct one controlled blast today at approximately 2:00 PM.