Joe Peed Pipe Installation, West Middleton Force Main Work, and CP-2 FRP Installation

14 de mayo de 2026

Construction Package 1 (CP-1)
At the Joe Peed Road site, Haren Construction crews will continue pipe installation activities. JF Wilkerson crews are not scheduled to be onsite today. Autry crews will continue force main work along West Middleton Drive.

Construction Package 2 (CP-2)
Park Construction crews will continue installing the 36-inch fiberglass reinforced pipe at the launch pit. Crews will also continue cutting in the temporary access road at the receiving pit outfall and are scheduled to begin receiving and placing stone this afternoon.

Carolina Drilling crews are scheduled to conduct one controlled blast today at approximately 2:00 PM.

Update: Blasting has been canceled for today.