Joe Peed Road Gravity Sewer Installation, West Middleton Force Main Work, and CP-2 Blasting Activity

20 de mayo de 2026

Construction Package 1 (CP-1)
At the Joe Peed Road site, Haren Construction crews will continue pipe installation activities. JF Wilkerson crews will continue laying gravity sewer main along Joe Peed Road. Autry crews will continue force main work along West Middleton Drive.

Construction Package 2 (CP-2)
Park Construction crews will continue installing the 36-inch fiberglass reinforced pipe at the launch pit.

Carolina Drilling crews are scheduled to conduct two controlled blasts today, with the first planned for approximately 11:00 AM and the second planned for approximately 2:00 PM.

Update:
Carolina Drilling has adjusted today’s controlled blasting schedule as crews continue coordinating field conditions and equipment needs.

The previously scheduled 11:00 AM controlled blast will not take place. One controlled blast remains scheduled for today at approximately 2:00 PM.

SGWASA appreciates the community’s continued patience as project crews continue this important infrastructure work.