Proyecto de ingeniería SGWASA

WTP Water Valve Replacement

Design is 100% complete, with an estimated construction cost of $710,000. The project remains on hold pending public bidding in 2026 and updates to the Capital Improvement Plan.

Presupuesto:

Design and evaluation: $155,980; estimated construction: $710,000

Hito actual:

Capital Improvement Plan, Project 101-10.

This project addresses recurring valve failures and leaks while improving bypass capability and system redundancy at the water treatment plant.

Design was 100% complete. Construction remained on hold pending public bidding and coordination with the updated Capital Improvement Plan.

Fondos:

SGWASA WTP Water Valve Replacement

Hazen & Sawyer

Recurring leaks and valve failures along the water main between the clearwell and finished-water pumps at SGWASA’s Water Treatment Plant highlighted erosion concerns and the need for improved bypass capability and system redundancy.

Hazen and Sawyer completed the evaluation of repair alternatives and preparation of design, permitting, and bidding documents. Evaluation and design costs totaled $155,980, with an estimated construction cost of $710,000.

As of October 2026, design was 100% complete. Construction remained on hold pending coordination with the updated Capital Improvement Plan, with public bidding planned for 2026.

Más información

Esta sección proporciona documentos de apoyo y multimedia relacionados con el proyecto. Los recursos a continuación consolidan información clave sobre el proyecto y temas estrechamente relacionados que orientan la planificación, el cumplimiento normativo y la coordinación.


Apoyo y recursos para proyectos

​

Utilice los enlaces rápidos de ingeniería para acceder fácilmente a la información del proyecto, ponerse en contacto con el equipo del proyecto y consultar los archivos del proyecto.

bottom of page