Proyecto de ingeniería SGWASA
I-85 Sanitary Sewer Improvement Project
CP1 - Increase wastewater system capacity through new pump stations and pipeline installation supporting long-term service reliability.
CP2 - Deliver the Southern Interceptor sewer construction package while managing funding and sequencing constraints.
Presupuesto:
CP1 - $34M CP2 - $30.24M (NTE award)
Hito actual:
CP2 construction began November 2025; interim financing is in place, and the Northern Interceptor is being reassessed.
Fondos:

CDM Smith, Haren Construction, Park Construction of NC, NC Department of Environmental Quality, United States Department of Agriculture, Town of Stem, Town of Butner, City of Creedmoor, Granville County
SGWASA serves southern Granville County, including Creedmoor, Butner, and Stem. Due to maxed-out wastewater system capacity, a development moratorium was enacted in 2018 for parts of Creedmoor and Butner. From 2019–2025, SGWASA collaborated with partners to design and fund a solution. CDM-Smith completed engineering plans and split the project into two construction packages: CP#1: Bid in July 2024; contract awarded to Haren Construction for $34.8M in December 2024. CP#2: Bid in May–June 2025. Total estimated project cost: $75 million.
CP#1 Status: ( In Progress/On Schedule): CP#1 includes the construction of two new sewer pump stations and the installation of new sewer pipe (gravity and force main). Haren Construction started construction on 4/1/25. Construction is on schedule and on budget.
c)
CP#2 Status: ( In Progress): A recommendation of contract award to Park Construction for the Southern Interceptor Sewer construction occurred at the October 14, 2025, Board of Directors meeting. The Board of Directors approved a contract with Park Construction NC, Inc., in the not-to exceed amount of $30,238,282. The project is funded in part by the United States of Agriculture (USDA). Construction for CP#2 started in November. A project timeline is shown below.
Note: Due to the proposed costs and budget constraints associated with the proposed work associated with CP#2, only the construction of the Southern Interceptor Sewer will be completed at this time. On September 5, the Finance Committee reviewed the $8M cost for the Northern Interceptor but made no funding decisions. Further discussion is planned by the Finance Committee at their upcoming meeting(s) .
Más información
Esta sección proporciona documentos de apoyo y multimedia relacionados con el proyecto. Los recursos a continuación consolidan información clave sobre el proyecto y temas estrechamente relacionados que orientan la planificación, el cumplimiento normativo y la coordinación.
Apoyo y recursos para proyectos
Utilice los enlaces rápidos de ingeniería para navegar fácilmente a la información del proyecto, comunicarse con el equipo del proyecto y ver los archivos del proyecto.